Administered by

  • HOME
  • CONTACT US
  • ABOUT THIS SITE
  • DISCLAIMER
  • Supported by
  • Australian Renewable Energy Agency (ARENA)
English (UK)
GB English (UK)
US English (US)
  • EXPLORE KNOWLEDGE BASE

  • CERI Knowledge Base

    • About the CERI knowledge base

      • Introduction to Australia’s electricity markets

        • Australian consumer insights

          • CER technical and interoperability standards

            • Connecting a customer to an electricity network

              • Connecting a generator to a distribution network

                • Utility interconnection (CSIP-AUS)

                  • Dynamic network export and generation control schemes

                    • Network load control schemes

                      • Network tariffs and network support services

                        • Participating in the National Electricity Market

                          • Participating in a frequency control market

                            • Participating in the RERT

                              • Participating in the Wholesale Electricity Market (Western Australia)

                                • Participating in the I-NTEM (NT)

                                  • Cyber security and data privacy arrangements

                                    • Consumer protection frameworks

                                    Load control requirements for EVSE in South Australia

                                    Last Updated on 23 July 2026

                                    SUGGEST AN EDIT

                                    LIKE THIS PAGE?

                                    Table of Contents

                                    What communication protocols must EVSE support? Requirements for vehicle-to-grid chargers Requirements for EVSE installations Purpose of Smarter Homes regulations Related articles

                                    The Smarter Homes regulations require that all new hard-wired EVSE installed in SA (residential or small-business sites) support remote demand response capabilities. To enforce this, the OTR has published a Technical Regulator Guideline, that specifies the technical requirements for installation of EVSE. Public charging stations and DC fast chargers are exempt from these requirements.

                                    What communication protocols must EVSE support?

                                    To qualify for registration, EVSE must support at least one approved demand response communication method:

                                    • OCPP 1.6 (J/v2 or higher):
                                    • ANSI/CTA‑2045-B (2021)

                                    Alternatively, the EVSE can be “Deemed to Comply” by the Regulator by any alternative method the regulator approves as equivalent.

                                    Requirements for vehicle-to-grid chargers

                                    From July 2026, vehicle-to-grid-capable EVSE must also support OCPP 2.1 and the forthcoming AS 5438 (CSIP-AUS) interoperability standard.

                                    Requirements for EVSE installations

                                    The OTR maintains a EVSE registered equipment compliance list that lists equipment approved and registered with the technical regulator. Installers are only permitted to install equipment that is on this approved equipment list, and installations with equipment not on this list are considered non-compliant.

                                    During installation, the installer must verify the charger supports either OCPP 1.6J or ANSI/CTA-2045-B protocols and can execute “load off” and “partial load” commands. EVSE is to be installed and configured in accordance with the OEM’s instructions but is not required to be tested on site with the SAPN or OTR through a capability test. OEMs must therefore ensure that they provide installers with clear information and instructions to simplify the installation process and mitigate any common issues with commissioning.

                                    Following installation, installation details are documented via the electronic certificate of compliance which links the installation to the installer in the OTR's database.

                                    Purpose of Smarter Homes regulations

                                    The Smarter Homes regulations are intended to ensure that residential EVSE can participate in future smart charging programs or enrol in a network load control scheme, although no such programs for EVSE are currently active in South Australia.

                                    Related articles

                                    • Network load control schemes
                                    • CER Technical and Interoperability Standards
                                    • Utility Interconnection (CSIP-AUS)
                                    • Load control via CSIP-AUS
                                    ev charging load management smarter homes capability guideline electricvehicles powerdistribution regulation

                                    Copyright 2026 – CERI.

                                    Knowledge Base Software powered by Helpjuice

                                    Expand